Leigh DB were appointed to refurbish and fit out a new multi faith room at Deloitte’s Leeds office in 1 City Square. The project required careful strip out, structural works, specialist finishes and mechanical and electrical installations. All works were completed within the allocated programme and in budget.

Pre-works preparation

Before starting the main refurbishment, Leigh DB carried out essential preparation:

  • Strip out of existing flooring, storage, shelving and plasterboard partitions
  • Electrical survey to assess existing systems
  • Removal and relocation of DBPP board
  • Removal of pin boards and signage, with all walls made good

"We are pleased to provide this testimonial in recognition of the outstanding work delivered by LeighDB on the recent Multi-Faith Facility project at Deloitte, Leeds. From the outset, LeighDB demonstrated a clear understanding of the sensitive and inclusive nature of the project. The team approached the task with professionalism, integrity, and a strong commitment to quality."

Lee Brophy – Small Works Project Manager – Mitie Projects

Fabric works and finishes

The refurbishment works involved transforming the space to Deloitte’s specification. Key tasks included:

  • Decoration of all walls and skirting to Deloitte standard
  • Installation of mirrors and acoustic wall panels
  • Substrate preparation, new vinyl flooring and carpet installation
  • Plumbing works for new water connection, integrated with existing drainage from adjacent toilets
  • Supply and installation of bespoke joinery, including a shoe storage unit with vinyl seat pad and back, an under-sink unit with bin store and undermounted sink, a bespoke Corian worktop surface with foot wash station, and floating shelves
  • Acoustic curtain track system and curtain, with ceiling strengthening and fixings
  • Installation of two new FD30 certified fire doors

Mechanical and electrical works

Specialist M&E services were delivered to support the new multi faith room:

  • Fire stopping works to the entire area
  • Leak detection works
  • Relocation of carbon monoxide detectors
  • Installation of water heaters and wastewater pumps
  • Floor access hatches for future maintenance of pumps and foot wash drainage
  • Relocation of electrics and installation of new lighting and emergency signage

Results of the Deloitte multi faith room refurbishment

Leigh DB successfully delivered a calm, functional and fully equipped multi faith space designed for staff wellbeing. Outcomes included:

  • A high quality finish completed in line with Deloitte specification
  • Practical joinery and storage solutions to support daily use
  • Acoustic treatments for privacy and comfort
  • Compliance with fire safety and building regulations
  • Project completed within programme and budget

"The project was delivered to a high standard, and with minimal disruption to the surrounding workspace. The finished facility reflects LeighDB’s dedication to thoughtful design, excellent workmanship, and a collaborative approach. We are proud of the outcome and grateful for their contribution to creating an inclusive space within Deloitte Leeds. We would not hesitate to recommend LeighDB for future projects."

Lee Brophy – Small Works Project Manager – Mitie Projects